The constructor was the “Gamesa Eolica”, a leader corporation in the field of green energy.
The origin of the generators’ parts was from different countries and the sea transport became with different vessels as well. The foundations originated from Spain, the towers from Spain and Italy, the blades from China, the nacelles from India.
Our company was selected among other competitors, to carry-out all relevant studies connected with the formalities and documentation as well as the safe and correct execution of the work, including the “Risk Assessment” the inward custom formalities from E.U. and third Countries as well, the exemption of inward tax.
Also the planning of the port of Pylos to accept those special equipment, the unloading from the vessels in the port, the provisional storage with proper guarding and protection, the reloading on the specialized trucks and all above under the specifications that required for this delicate equipment.